And, here's the first build update!   ;D


This is my humble machining area!  It took me ~3 months to acquire, install, and setup:

[ATTACH=full]55741[/ATTACH]


I bought all raw materials from eBay - 6061 aluminum and stainless steel:

[ATTACH=full]55742[/ATTACH]


Here's the first shop drawing! 

[ATTACH=full]55743[/ATTACH]


This project required a 4-jaw chuck to hold the square stock.  This was the first facing operation on the ED-209!

[ATTACH=full]55744[/ATTACH]


I learned quickly that machining required tools.  Lots and lots of tools.  I built tools to build tools that helped me to build the actual parts.  Seriously.  Here you see the "T" stop I made and a tapping guide.  The tapping guide was critical to keep from breaking $8 #2-56 taps:

[ATTACH=full]55745[/ATTACH]


First holes drilled and tapped:

[ATTACH=full]55746[/ATTACH]


This is the start of the footpad.  I turned a section of 2"x2"x1/4" aluminum to get the final part:

[ATTACH=full]55747[/ATTACH]


[ATTACH=full]55748[/ATTACH]


After some milling (sorry for the blur):

[ATTACH=full]55749[/ATTACH]


Here's the first assembly:

[ATTACH=full]55750[/ATTACH]


I'll have some build time this weekend.  I'll post an update for sure.  Thanks for following along!